Using Open Project, how can one calculate staff-hours?
Using Project -> Project Information -> Statistics
, is work
it? ("Work" is 1,219 hours in my example below)
Using Open Project, how can one calculate staff-hours? Using |
||||
|
Work is indeed effort-hours, rather than duration. Someone works for two hours on a task over two days results in 2 work hours, and 2 Days of duration. |
|||
|