Tell me more ×
Project Management Stack Exchange is a question and answer site for project managers. It's 100% free, no registration required.

Using Open Project, how can one calculate staff-hours?

Using Project -> Project Information -> Statistics, is work it? ("Work" is 1,219 hours in my example below)

enter image description here

share|improve this question

1 Answer

Work is indeed effort-hours, rather than duration. Someone works for two hours on a task over two days results in 2 work hours, and 2 Days of duration.

share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.