338 views

Setting Deadlines in software development [duplicate]

I have been working on a system alone for about two years. I inherited the system from a contractor who spent about two years working on it before me (alone). The system is not particularly well ...
4
votes
4answers
214 views

What do you do to estimates for agile stories where developers are pair programming?

If it was a 2-point story for one person, would you double it if people are pairing? Pairing isn't always necessarily done 100% of a dev task, so it seems that doubling the story points seems ...
5
votes
2answers
282 views

Is it okay to add time for “unexpected delays” to a time estimate?

I've landed my first contract (hooray, self employment!) and the company is asking for time estimates. Programmers are notoriously bad at time estimates, and I know I've been laughably wrong ...
0
votes
1answer
192 views

Are t-shirt estimates a good way to conduct initial estimates? [closed]

I've read articles with very conflicting arguments on t-shirt estimates. Neither article seemed all that credible so I thought I would bring this up here. Are t-shirt estimates a good idea? For ...
1
vote
2answers
103 views

How to factor in responsive design when providing an estimate for web applications?

In the past usually I have only had to estimate web applications based on browser support. But for more recent projects device and platform support are also very important as well (screen ...
8
votes
5answers
393 views

The Relative Cost Efficiency of (Acceptance) Test Driven Development

I would like to know what the overall impact of resource planning on a software project is, where the requirements and design of the project are driven by automated acceptance tests and unit tests, in ...
0
votes
2answers
127 views

estimation method at the “just finished definition phase”

We are basically using Waterfall life cycle methodology. Requirement Analysis: I get a use case created by some one else. Design (talking only about Low level design): I get some little feeling about ...
-4
votes
1answer
83 views

Web Application Tasks Estimation [closed]

I know the answer depends on the exact project and its requirements but i am asking on the avarage % of the total time goes into the tasks of the web application development statistically from your ...
4
votes
4answers
120 views

Independency and estimation of user stories that rely on shared predecessor

Lest's say I have user stories about using product catalog in shop: As an administrator I can add/modify/delete catalog items (one or more user story, doesn't matter here) As a customer I can search ...
5
votes
2answers
367 views

How do I survive in a Waterfall world? [duplicate]

I currently work in a company where the Waterfall model is deeply ingrained. We are pushing Agile principles but it's a long process. Meanwhile, I have to work in a Waterfall world with sequential ...
1
vote
2answers
371 views

How to ensure a project 100% tested?

I want to know how exactly, we can ensure that a project is 100% tested ? In banking or financial applications not 1% also tolerable. So being a developer, how can you say your code is 100% tested? ...
2
votes
2answers
1k views

Closest Point of Approach (CPA) mathematical formula in ship radar

I was recently searching for the mathematical formula to find closest point of approach (CPA) between one ship and another ship. I need to apply the formula in my radar ship program and I can't find ...
9
votes
11answers
753 views

User stories are too high level and conceptual, management expects developers to fill in the blanks

I am employed in a very brilliant company with a true intention of doing XP. Communication is good and management is open to constructive discussion but due to pressing time constraints, some certain ...
0
votes
1answer
73 views

Tool helping with estimations [closed]

I am looking for a tool supporting me with estimations. What I would like to do is to specify a higher level task and break it into several smaller tasks. When a task is small enough, I could assign ...
4
votes
2answers
312 views

Efficient way to create a code estimation/technical specification in a fast-moving environment

To better understand my question, let me elaborate the background of the subject matter. I work in a financial institution where the business module (credit finance) is constantly changing. In the IT ...